Ellendale is still a sequencing problem: power, then hall, then tenant

Applied Digital’s North Dakota campus is the beat. The July 10-K describes development. It does not describe a finished offtake stack.

Summary

Applied Digital filed its Form 10-K on July 29 and an earnings 8-K two days earlier. Ellendale remains a rural MISO-adjacent campus where the order of operations has not changed: delivery, then white space, then a tenant who can actually take the hall. Jamestown is the standing plant. Treating the two as one contracted HPC region is how the week gets misread. June’s Item 1.01 packages are real paper. They are not a substitute for a named, energized lease.

Why it matters

Developers in this coverage set get pulled into the same multiple as operating GPU clouds. Applied Digital is a campus company. The 10-K is the place to watch sequencing — not a social post about North Dakota.

Companies affected

Risks

  • Substation and delivery slip move COD without a matching customer headline.
  • Item 1.01 agreements can be financing rather than offtake. Read the items.
  • Jamestown conversion is optional. A standing miner is not an HPC lease.